Drainage improvement
Poor drainage along the railway causes flooding along the path and under the railway bridge.
With few materials, blood, sweat and tears and some on-the-spot engineering calculations, the team improved the area greatly.
Within just 3 weeks the team:
-
dug drainage channels,
-
dredged the existing stream and ditches,
-
made a rampart along the edge of the railway embankment,
-
raised a section of the pathway to allow a walkway through the puddles.
-
dug a channel under the bridge to guide the water off the railway embankment into the stream.
We used old paving slabs to provide foot paths over the drainage channels.